The state of North Carolina has set aside $40 million to rebuild the Fayetteville State Veterans Home on Cochran Avenue — a facility that was shuttered in December 2023 after officials found structural problems, water intrusion and mold that forced relocation of its residents. The appropriation was included in the budget Gov. Josh Stein signed in July, but a provision requiring the Department of Military and Veterans Affairs to repay the state has drawn objections from at least one lawmaker representing parts of Cumberland County.
Funding split and scope
The allocation arrives as a two-year commitment from the state. The budget earmarks $10 million for the 2026-27 fiscal year and $30 million for 2027-28, for a total of $40 million to rebuild the facility that had housed 85 residents before its closure. The appropriation equals roughly 0.12% of the state's $34 billion budget.
| Fiscal year | Amount |
|---|---|
| 2026-27 | $10,000,000 |
| 2027-28 | $30,000,000 |
| Total | $40,000,000 |
Repayment provision and criticism
Under the budget language, the Department of Military and Veterans Affairs must repay the appropriation to the State Capital and Infrastructure Fund through annual transfers ranging from $1 million to $15 million once the project is completed. That repayment schedule — not the rebuild itself — is the pivot point for concern among some local legislators.
"I'm hoping somewhere along the line that can be corrected," said Sen. Val Applewhite, who represents part of Cumberland County and described herself as glad the home will be rebuilt but opposed to the repayment requirement.
Sen. Applewhite's comments reflect a friction between delivering capital improvements for veterans and placing long-term budget obligations on the agency charged with running veterans services. The Department of Military and Veterans Affairs operates several state veterans homes and must manage both ongoing care and any financial liabilities tied to capital projects.
Local consequences and context
The closure in late 2023 displaced all 85 residents at the Cochran Avenue home. Officials moved those veterans to other state veterans homes or nearby nursing facilities. A September 2023 letter to the State Construction Office documented water intrusion and reported mold throughout the facility — conditions that prompted the relocation.
For families and local advocates, the news that the state will fund reconstruction will be welcome, but the repayment requirement raises practical questions about operations and future services. If the department must divert general funds to repay the capital appropriation, that could affect maintenance, staffing, or programming across other veterans facilities — issues that local veterans groups and lawmakers may press on in the months ahead.
- Immediate impact: Rebuilding will restore a veterans-specific care option in Fayetteville after the 2023 closure.
- Financial mechanics: Repayment obligations fall to the Department of Military and Veterans Affairs, potentially affecting departmental budgets.
- Political debate: Some local lawmakers supported the funding; at least one criticized the repayment clause and hopes for legislative change.
What comes next
With the budget finalized, planning and design work for the rebuild will be the logical next steps. The repayment schedule will not begin until after project completion, according to the budget language; how long that takes will determine when the department's transfers to the State Capital and Infrastructure Fund must start. Lawmakers who supported the appropriation but object to the repayment clause have indicated they may seek to alter the requirement in future sessions.
For Fayetteville residents and veterans who were affected by the closure, the state's appropriation is progress toward restoring local capacity. The repayment provision, however, leaves open an unresolved policy question about how to balance capital investment with the financial health of the agency responsible for veterans' care.